Those of you who have started looking for a plot
for your self-build project will know that finding the right one
in your chosen area involves a lot of time and effort and not a
few disappointments. This explains why those who have a sizeable
garden and like the area that they live in use part of their garden
for their self-build project.
This is how Steve McGlasson and his wife came to
self-build. Moving to a village in Northamptonshire some six years
ago they extended their bungalow both outwards and upwards. The
house was still not the home they were looking for and so decided
the only way to achieve exactly what they wanted was to build their
own four-bedroom house in the back garden.
Obtaining planning permission hit a snag when the
council objected to the proposal because the plot was just outside
of the village boundary. However, the case was argued, including
the fact that a new development of houses had been built adjacent
to the plot in the six years they had been there. With the backing
of the parish council, the planning department approved the plans
without having to go through the appeal procedure. Access to the
site had to be improved by buying small sections of the neighbouring
gardens to increase the width of the drive, which is very steep.
Steve is managing the project and doing much of
the work himself. He has employed a builder to work full time and
is sourcing sub contractors as and when needed. As a plumber, he
will obviously be carrying out that side of the build and employing
tradesmen that he knows to be reputable. In fact, the same builder
and carpenter also undertook the conversion work on his bungalow.
The site itself is gently sloping and needed only a few small trees
removed in way of clearance. The foundations are 1,000mm deep in
sandy soil and of poured concrete. The concrete needed to be pumped
due to the steep driveway accessing the site.
Traditional construction is being used, with 65mm
of dry thermal insulation between skins. The floor is of beam and
block with blockwork interior walls on the ground floor. A batch
of 20,000 Baggeridge Arizona bricks for the outer skin was bought
that are slightly darker than the usual colour. This gives the house
an aged appearance fitting to the village, compared
to the new, brighter red bricked development adjacent.
The sitting room, situated to the rear overlooking
the back garden, features an open fireplace. The chimney was originally
fitted with an 8 flue which is suitable for gas, but Steve
also wanted provision made for a solid fuel fire. This meant enlarging
the chimney by scraping some of the rear block faces away to accommodate
the 11 flue required for solid fuel fires.
A condensing boiler is planned for the central
heating, which will be underfloor on the ground floor and radiators
on the first. Provision has been made for the underfloor heating
to be extended into a conservatory if required at a later date.
I would prefer to fit a condensing boiler because they are
now the most economical form of heating and seem to have improved
in reliability considerably since the first models were on the market,
said Steve. The remainder of the plumbing work includes two ensuite
bedrooms and a downstairs toilet.
To the front of the house foundations have been
laid for a two-car garage, again to be faced with Baggeridge Amazon
bricks. The back garden has been cleared, it had a layer of topsoil
and now just awaits grass seed for the lawn. A new fence has also
been erected. This is because the rear of the plot backs onto a
playing field and is to discourage children from using the site
as a playground and so avoid potential accidents.
So far with the build the only real snag
we have met is the electricity supply which has had to be rerouted
via the playing field to the back of the house rather than use the
original supply which came from the front. The difference in cost
between the two sources was £2,000, so it made good sense
to take the rerouting option, commented Steve.
To date, the build has reached just below roof
height and it is hoped that the roof will be on during March 2002.
There is no real time limit to this build and Steve has some further
work to carry out on their converted bungalow such as building a
garage, surfacing the driveway and some landscaping before it is
put on the market.
|